โ HOW TO: Split a package activity into separate guest groups
Use Split Activity when guests on the same package need separate activity arrangementsโfor example, two guests want a morning tour and another wants the afternoon departure. Each group gets its own activity plan while staying under the same package.
A package activity is one activity included in a package, such as snorkeling or a spa treatment. The package header holds the overall package details and sold price.
Before you start
You can split an activity when all of these conditions are met:
- You are editing an activity within a package, rather than the package header.
- At least two guests are going on that activity.
- The activity has not been cancelled.
Check who needs to stay together and who needs a separate arrangement before applying the split.
How to apply a split
- Go to Activity Plans and open the package activity you want to split. For example, open the snorkeling activity rather than the overall package.
- Open the activityโs Actions menu.
- Select Split Activity.
- Choose the number of groups. You can create at least two groups, up to the number of guests going on the activity.
- Assign each guest to exactly one group. Every group must have at least one guest.
- Review the assignments, then click Confirm to apply the split.
- Check the resulting activity plans under the package. The original activity becomes the first group; each additional group appears as another linked activity with its own guest list.
Manage each group after the split
The split separates the guest lists. You can then schedule or manage each resulting activity independently. Review each groupโs activity, provider, date, time and participants, and save any further edits.
Changing the guest list on one split activity does not automatically change the guest lists on the others. Check each activity separately, including any Added Items such as meals or equipment.
Example: Three guests have snorkeling included in their package. Assign two guests to Group 1 and the remaining guest to Group 2, then confirm the split. Schedule Group 1 for 9:00 AM and Group 2 for 11:00 AM. Both activity plans remain linked to the same package.
Review the guest itinerary and the operational information your team or provider will use after making changes.
What happens to the price?
Splitting does not change the package price or add another charge. The sold price stays on the package header. The individual split activities show zero line pricing because they are separate operational arrangements within the same purchase.
FAQ
Does confirming a split automatically give each group a different time?
The split creates separate activity plans with their own guest lists. Review and set the intended time on each resulting plan.
Can I split an activity again?
Yes, if at least two guests remain on that activity, it has not been cancelled.
Does splitting change the other activities in the package?
Each split activity has its own guest assignments. Splitting one activity does not change the guest lists on the other package activities.
Is splitting the same as changing Qty in package setup?
No. Qty determines how many copies of an activity are created when the package is booked. Split Activity separates the participants on an existing package activity into groups.
Can I use โCustom time for this guestโ to separate one participant?
That option changes the selected activity booking, which may include several participants. Apply the split first when only part of the booking group needs another time.
Troubleshooting
Split Activity is not available
Check that you opened a package activity rather than the package header. Confirm that at least two guests are going and the activity is not cancelled. If it meets these conditions and the option is still missing, contact your administrator or Planniac Support.
The guest assignments are incomplete
Review every guest on the split screen. Assign each person to exactly one group and make sure no group is empty before clicking Confirm.
A resulting activity has no time
Ask your administrator to check that the provider has an active schedule or timeslot covering the activity date. Update the activity plan with the intended available time and check the saved result.
The split activities show a zero price
This is expected for included package activities. Check the package header for the sold package price; splitting does not create additional charges.